Talimarjan Combined Cycle Power Plant — Power Plant Switchboard Project

The Talimarjan Gas-Fired Combined Cycle Power Plant in Uzbekistan combines gas turbines with a steam cycle to generate electricity. Devpan supplied Dev24/36 medium-voltage switchgear, the auxiliary main distribution and MCCs.

Power plantTalimarjan Gas-Fired Combined Cycle Power Plant — Power plant, Uzbekistan — Devpan
Technical Summary

Electrical Profile of the Project

  • LocationUzbekistan
  • Building typePower plant
  • Installed power≈ 10,000 kVA
  • Transformer configuration4 × 2,500 kVA
  • Main busbar rated current2 × 4,000 A
  • Short-time withstand current (Icw)80 kA / 1 s
  • Devpan scopeMedium voltage switchgear, low voltage switchboards and engineering
  • Verification standardIEC 61439-1, IEC 61439-2
About the Project

About the Project

In a combined cycle plant, the auxiliary power system feeds the loads that keep the units running: boiler feed pumps, cooling tower fans, lube oil and fuel gas systems. A loss of supply to these auxiliaries can trip a unit and take generation off the grid. Very hot summers, cold winters, dust and continuous duty all call for extra margin when selecting switchgear and control equipment.

For a plant of this scale, a typical architecture builds the 10 kV auxiliary bus with Dev24/36 metal-enclosed modular switchgear and feeds a 2 × 4,000 A low-voltage main distribution through four 2,500 kVA transformers. Auxiliary motors are grouped in redundant A/B trains in Form 4b, IP54 DevControl MCCs. Two 1,500 kVA emergency generators cover safe shutdown and restart loads, while DevComp panels balance reactive power.

Scope

Devpan Scope and Switchboard Architecture

Devpan’s scope extends from the 10 kV auxiliary distribution to the motors of the plant’s auxiliary systems.

  • Medium-voltage switchgear (Dev24/36): metal-enclosed modular panels with 24 kV insulation, operated at 10 kV, for transformer and large motor feeders.
  • Main distribution boards (DevPanel): 2 × 4,000 A, 80 kA / 1 s, Form 4b, auxiliary distribution with bus coupler.
  • Motor control centres (DevControl): IP54, withdrawable, redundant A/B trains for feedwater, cooling, lube oil and fuel gas systems.
  • Power factor correction (DevComp): stepped compensation for auxiliary motor loads.
  • Sub-distribution boards (DevBox): control building, workshop and ancillary buildings.
Technical Configuration

Technical Configuration

Installed power≈ 10,000 kVA
Transformer configuration4 × 2,500 kVA
Medium voltage level10 kV (Dev24/36)
Low voltage / frequency400 / 230 V, 50 Hz
Main busbar rated current2 × 4,000 A
Short-time withstand current (Icw)80 kA / 1 s
Form of internal separationForm 4b
Degree of protection (IP)IP54
Generator back-up2 × 1,500 kVA
Verification standardIEC 61439-1, IEC 61439-2
Engineering

Project-Specific Engineering Topics

Redundant A/B auxiliaries

Duty and standby pumps and fans are fed from different sections, so a single busbar fault does not stop the unit.

Safe shutdown supplies

Lube oil, turning gear and emergency cooling loads are fed from a generator-backed emergency section.

Short-circuit withstand

Large auxiliary transformers produce high fault currents; busbars rated 80 kA / 1 s are selected accordingly.

Harsh site conditions

IP54 enclosures protect against dust and temperature swings and improve reliability under continuous duty.

FAQ

Frequently Asked Questions

What is the auxiliary power for the Talimarjan plant?

For a combined cycle plant of this scale the auxiliary installed power is approximately 10,000 kVA, with a typical transformer configuration of 4 × 2,500 kVA. The LV main busbar is planned at 2 × 4,000 A and 80 kA / 1 s, MV distribution at 10 kV uses Dev24/36 switchgear, and emergency power comes from 2 × 1,500 kVA generators.

Why use Dev24/36 switchgear on a 10 kV system?

A 24 kV insulation level gives a generous margin at 10 kV operation, which translates into long service life and high operational safety in a dusty, hot plant environment.

Why are auxiliary motors split into A/B trains?

Feeding redundant pumps and fans from separate sections ensures that a single board or busbar fault cannot halt generation.

Do you have a project of a similar scale?

Send us your single-line diagram, your transformer rating or simply your load list. Our engineering team runs the short-circuit and discrimination study and defines the form of separation and busbar cross-section with you.

Request a quotation